Get the latest price? We will reply as soon as possible (within 12 hours)

Oil Well Pump Inspection Workflow: Rod Pump Workover Guide (Part 2)

2026-03-12

In Part 1, we discussed the causes of pump failures and the preparation procedures required before starting an oil well pump inspection operation.

Once the rod string has been pulled from the well, the workover operation enters its most critical phase: tubing removal, pump inspection, and system reinstallation.

These stages determine whether the rod pump workover will successfully restore production or lead to additional operational risks.

This article explains the remaining steps of the pump inspection process used in modern oilfields.


What Happens After the Rod String Is Pulled?

After removing the rod string, technicians must prepare the well for tubing removal and pump inspection.

This stage involves several key procedures designed to ensure safe well control and accurate equipment diagnosis.


Opening the Tubing Drain

Before pulling the tubing string, the tubing column must be drained.

A steel rod or specialized tool is lowered into the tubing to activate the tubing drain valve, allowing the fluid inside the tubing to flow back into the wellbore.

This step reduces internal pressure and prevents large volumes of liquid from being lifted to the surface during tubing removal.

Proper drainage significantly improves safety and lifting efficiency during rod pump workover operations.


Oil Well Pump


Removing the Wellhead and Installing Well Control Equipment

Once the tubing has been drained, the wellhead assembly can be removed.

Typical operations include:

  • Removing the Christmas tree or wellhead equipment

  • Installing a well control device or blowout preventer

  • Sealing the wellhead during tubing operations

These measures help prevent well kicks, fluid leakage, or environmental contamination during the workover process.

Well servicing operations commonly require removing surface equipment and pulling rods or tubing to restore production performance.


Pulling the Tubing String

After well control equipment is installed, crews begin pulling the tubing string.

Tubing removal is performed joint by joint using elevators and power tongs.

Typical operational steps include:

  • Lifting the tubing joint with tubing elevators

  • Breaking the threaded connection using power tongs

  • Racking the tubing on a pipe rack

  • Repeating the process until the entire tubing string is removed

This procedure must be carried out carefully to avoid damaging tubing threads or dropping tools into the well.

During workover operations, tubing joints are lifted, connected, and installed or removed using specialized handling equipment such as elevators, slips, and power tongs.


Tubing and Rod Inspection Procedures

After the tubing string is pulled from the well, technicians perform a detailed inspection.

Key inspection items include:

  • Tubing wall corrosion

  • Thread damage

  • Mechanical deformation

  • Sand erosion

  • Wax buildup


Understanding these wear patterns helps engineers determine the root cause of pump failure and optimize future well operations.

For example:

  • Excessive coupling wear may indicate rod buckling

  • Sand erosion may reveal formation sand production

  • Severe corrosion may require upgraded material selection

These diagnostic insights are essential for planning effective sucker rod pump repair operations.


Sucker Rod Pump Inspection and Testing

Once the tubing is removed, the sucker rod pump can be retrieved and inspected.

Technicians evaluate the following components:

  • Pump barrel condition

  • Plunger surface wear

  • Standing valve integrity

  • Traveling valve performance

  • Seal and thread conditions

The plunger should move smoothly inside the pump barrel without sticking or excessive clearance.

Before running the pump back into the well, technicians typically perform a manual pump test to verify suction and sealing performance.

If the pump fails inspection, it must be repaired or replaced before reinstalling the system.


Reconfiguring the Tubing String

After inspection and repair, the next step is tubing string configuration.

Proper tubing design is critical for ensuring long-term pump performance.

Engineers must calculate several key parameters:

Pump Setting Depth

Pump depth is determined using a combination of:

  • tubing hanger length

  • tubing string length

  • pump length

  • drain valve length

Accurate pump depth ensures the pump operates within the optimal fluid column.


Tailpipe Depth

In wells with sand production, a tailpipe and sand filter may be installed below the pump.

This configuration helps prevent sand from entering the pump chamber and causing sand lock.


Rod String Configuration

Rod string design must consider several factors:

  • well depth

  • pump size

  • production load

  • rod strength

Proper rod string configuration helps minimize fatigue failure and rod buckling, extending equipment life.


Running the Tubing Back Into the Well

After the tubing string has been inspected and configured, it is run back into the well.

The installation process typically includes:

  • cleaning the tubing

  • applying thread compound

  • tightening threaded connections

  • lowering tubing into the wellbore

Each tubing joint must be properly torqued to prevent thread leakage or connection failure.

Proper tubing installation is essential for maintaining well integrity and efficient production.


Installing the Rod String and Pump Assembly

After the tubing string is installed, the rod string and pump assembly are lowered into the well.

The plunger must enter the pump barrel smoothly to avoid damaging the pump.

Operators must lower the rod string slowly while monitoring for abnormal resistance.

If the well includes a rod pump release mechanism, it must be properly connected during this stage.


Pump Pressure Testing and Commissioning

Before restarting production, the system must undergo a pressure test.

Typical test parameters include:

pump pressure stabilization

pressure holding time

pressure drop evaluation

If the pressure drop remains within acceptable limits, the pump system is considered operational.

Operators then reconnect the pumping unit and begin trial pumping operations.


Final Well Startup and Handover

Once the pump system passes testing, the well is returned to production.

Final procedures include:

  • tightening all wellhead bolts

  • cleaning the wellsite

  • reconnecting production flowlines

  • verifying pumping unit alignment

After the workover operation is completed, the well is formally handed back to the production team with all operational records documented.


Engineering Insight: Reducing Pump Workover Frequency

For oilfield operators, reducing the frequency of rod pump workover operations is a major goal.

Frequent workovers increase operational costs and cause production downtime.

Many modern oilfield equipment manufacturers now provide high-durability rod pump systems, wear-resistant tubing materials, and advanced downhole tools designed to extend pump service life.

By combining reliable equipment with optimized maintenance strategies, operators can significantly reduce oil well pump inspection frequency and improve overall field productivity.


Conclusion

Oil well pump inspection is one of the most important maintenance operations in rod pumping systems.

A successful rod pump workover operation requires careful planning, precise equipment inspection, and strict adherence to safety procedures.

When performed correctly, pump inspection workovers can:

  • Restore well productivity

  • Extend equipment lifespan

  • Reduce long-term operating costs

  • Improve production stability

Understanding the complete workflow of oil well pump inspection and sucker rod pump repair allows operators to maintain efficient and reliable oil production.


FAQ

How often should an oil well pump be inspected?
Most oilfields schedule pump inspections every 1–3 years, depending on well conditions and pump performance.


What is a rod pump workover?
A rod pump workover is a maintenance operation that involves pulling the rod string and tubing to inspect or repair the sucker rod pump.


What are the most common rod pump failures?
The most common failures include sand lock, wax blockage, rod fatigue, valve leakage, and tubing wear.